Generator step up transformers

request for proposal (rfp) for generator step up transformers (gsu), step-down distribution transformers & station service transformers for four (4) kenyan shp’s
we have been pre-qualified as a successful proponent for epc contract to develop following small hydroelectric projects in kenya.
1. south mara – 2 mw
2. north mathioya – 5 kw
3. lower nyamindi – 1.8 mw
4. iraru – 1.5 mw